Great progress is being made at IDI Gazeley‘s flagship distribution park at Magna Park Milton Keynes. The infrastructure project for phase 2 of the park commenced in May 2017 and includes a site wide cut and fill of more than 270,000 m.cu, enough to fill the Royal Albert Hall three times over. Lysander are appointed to IDI Gazeley as Project Manager for the works which are due for completion in November 2017, with on plot construction of the 574,000 sq.ft unit commencing in August 2017.